How many men are required to complete the job in 3 hours?

Prepare for the USTET Mental Ability Test with our quiz. Study with varied questions, detailed explanations, and insightful hints. Enhance your mental ability and get ready for the exam!

Multiple Choice

How many men are required to complete the job in 3 hours?

Explanation:
To determine how many men are needed to complete a job in a specific amount of time, we can employ the concept of "man-hours." A man-hour is a unit that represents the work done by one person in one hour. Let's assume the job requires a certain total number of man-hours to complete. If we denote the total man-hours required to complete the job as \(M\), then if we want the job done in 3 hours with \(N\) men, we can set up the equation as follows: \[ N \times 3 \text{ hours} = M \] From this equation, rearranging gives us: \[ N = \frac{M}{3} \] If we already know the total man-hours needed to finish the job within a longer duration with a certain number of men, we can then calculate how many men would be necessary to finish the job in 3 hours. For instance, if the job initially requires 60 man-hours in total and you want to find out how many men are required to finish it in 3 hours: Set up the equation: \[ N \times 3 = 60 \] Solving for \(N\) gives: \[ N = \frac{60

To determine how many men are needed to complete a job in a specific amount of time, we can employ the concept of "man-hours." A man-hour is a unit that represents the work done by one person in one hour.

Let's assume the job requires a certain total number of man-hours to complete. If we denote the total man-hours required to complete the job as (M), then if we want the job done in 3 hours with (N) men, we can set up the equation as follows:

[ N \times 3 \text{ hours} = M ]

From this equation, rearranging gives us:

[ N = \frac{M}{3} ]

If we already know the total man-hours needed to finish the job within a longer duration with a certain number of men, we can then calculate how many men would be necessary to finish the job in 3 hours.

For instance, if the job initially requires 60 man-hours in total and you want to find out how many men are required to finish it in 3 hours:

Set up the equation:

[ N \times 3 = 60 ]

Solving for (N) gives:

[ N = \frac{60